This is a job Jerry
and I did recently. 
It was 88 ft. of hairpin/picket fencing with finials and collars on every picket. 
Also, 2 swing gates .We found item# FCS-89 in the Cunningham books, and it estimated one hour per running foot to fabricate this style of fencing.  Jerry and I had it fabricated, primed, painted and installed in 4 1/2 days.  

ASK
ME
HOW!


This is a job Chris fabricated and installed himself.  
The only thing I did was provide him detailed drawings based on his field measurements.
There were 2 sets of gates on this job. 
This was also Chris' first driveway gate job.
 A-Plus Welding and Fabrication
Fronz Roberts

This is item# ER821 in the Cunningham Books.  There was 109 linear ft. on this job, with 80 ft. straight and the rest raked.  No painting, no installing.  Just delivered.  Fronz and I spent 2 1/2 days fabricating (31 man hours) and 4 hours loading, delivering and unloading.  We also made bolt-on connections which the books don't mention and still beat their time by 75 hours.

ASK
ME
HOW!
Here's another one Chris fabricated and installed.  Again, all I did was provide him with a set of drawings from his field measurements.